ENGINE - ENGINE AND EMISSION CONTROL - EMISSION CONTROL<4N1> - EXHAUST GAS RECIRCULATION (EGR) SYSTEM - EGR VALVE AND EGR COOLER
EGR VALVE AND EGR COOLER REMOVAL AND INSTALLATION
N502630510000B00ENG
Pre-removal Operation
Post-installation Operation
Removal steps
1.
Water hose A (Refer to Engine – Engine Cooling – WATER HOSE AND WATER PIPE REMOVAL AND INSTALLATION)
2.
Water hose B (Refer to Engine – Engine Cooling – WATER HOSE AND WATER PIPE REMOVAL AND INSTALLATION)
3.
EGR valve connector connection
4.
EGR valve pipe B
5.
EGR tube gasket
6.
EGR valve pipe gasket on EGR cooler bypass valve side
7.
Harness bracket
8.
EGR valve
9.
EGR valve gasket
10.
Vacuum hose A (EGR cooler bypass valve side) connection (Refer to Engine – Engine Overhaul <4N1> – SOLENOID VALVE AND VACUUM HOSE REMOVAL AND INSTALLATION)
11.
EGR valve pipe A
12.
EGR valve pipe gasket on EGR cooler bypass valve side
13.
EGR valve pipe gasket on inlet manifold side
14.
Water hose C (water pipe C side) connection (Refer to Engine – Engine Cooling – WATER HOSE AND WATER PIPE REMOVAL AND INSTALLATION)
15.
Water pipe B bracket connection on inlet manifold side (Refer to Engine – Engine Cooling – WATER HOSE AND WATER PIPE REMOVAL AND INSTALLATION)
16.
EGR cooler bypass valve
17.
Stud
18.
EGR cooler bypass valve gasket
19.
Water hose F connection on EGR cooler side
20.
Water hose E connection on EGR cooler side
•
Fuel return pipe A (Refer to Engine – Diesel Fuel – SUPPLY PUMP REMOVAL AND INSTALLATION)
21.
EGR cooler
INSTALLATION SERVICE POINT
>>A<< EGR COOLER BYPASS VALVE GASKET/EGR COOLER BYPASS VALVE/EGR VALVE PIPE A GASKET (INLET MANIFOLD SIDE)/EGR VALVE PIPE A GASKET (EGR COOLER BYPASS VALVE SIDE)/EGR VALVE PIPE A/EGR VALVE GASKET/EGR VALVE/HARNESS BRACKET/EGR VALVE PIPE B GASKET (EGR COOLER BYPASS VALVE SIDE)/EGR TUBE GASKET/EGR VALVE PIPE B INSTLLATION
Temporarily tighten each part. Make sure that each gasket is installed with its projection being positioned as shown.
Check that there is no clearance among each component. Temporarily tighten the bolts and nuts to the target torque in the order of number 3, 2, 7, 8, 10 as shown in the figure.
Temporary tightening torque: 10 N·m (Target)
Tighten each mounting bolts to the specified torque in the order as shown in the figure.
Tightening torque: 20 ± 2 N·m