Check the tube for leaking by the following procedures.
Connect the joint to connector (b) or connector (c).
Connect the connection of connector (b) and connector (c).
Disconnect the connection of connector (d) and connector (e).
Remove the joint connecting connector (d) and connector (e), then install the joint to the hand pump (positive pressure type).
Connect the hand pump (positive pressure type) to connector (d).
Apply a pressure of 50 kPa to connector (d) and check that the pressure is maintained for 30 seconds or more.
When the pressure is maintained, the tube is not leaking. Go to Step 2.
When the pressure is not maintained, the tube is leaking. Replace the urea line tube B, then go to urea line tube C check.
Check the tube for clogging by the following procedures.
Disconnect the connection of connector (b) and connector (c).
Apply pressure to connector (d) using the hand pump (positive pressure type).
When the pressure is not maintained, the tube is not clogged. Connect connector (b) and connector (c), then go to urea line tube C check.
When the pressure is maintained, the tube is clogged. Replace the urea line tube B and connect connector (b) and connector (c), then go to urea line tube C check.